iTeam Order Status
When you log into iTeam, your experience will be similar to what you see below. Your project dates are tied directly into Vetor's internal project system. Your data is always 100% accurate..
Project Number: |
Your Project Number Here |
---|---|
Customer: |
Your Company |
Machine Type: |
Flo-Coater VFC-200MX |
Vector Project Manager: |
Your Project Manager Here |
Project Status | Status |
---|---|
Mechanical Release to Manufacturing : |
Done |
Control System Release to Manufacturing: |
Done |
P&ID & Interconnect Drawing Package: |
Done |
Software Functional Specifications: |
February 1, 2010 |
Software Ready for Floor Checkout: |
March 1, 2010 |
Validation Test Plans: |
March 1, 2010 |
Equipment Assembly Start: |
April 1, 2010 |
Begin Internal Testing: |
May 1, 2010 |
Customer FAT: |
May 15, 2010 |
Planned Ship Date: |
June 1, 2010 |